The agreement was signed by EWE Chairman Stefan Dohler and Tesa CEO Dr. Kourosh Bahrami.
The hydrogen will be produced at EWE’s 320-MW generation plant in Emden, which is scheduled to begin operations at the end of 2027. It will be produced via electrolysis using renewable electricity. The hydrogen is expected to meet European requirements for RFNBO (Renewable Fuels of Non-Biological Origin). From Emden, theH2 will be transported to Hamburg via the emerging core network.

A hydrogen production plant with a capacity of 320 MW is currently under construction in Emden. © Arge CHC Ostfriesland
Tesa Combines Electrification and Hydrogen
According to the company, the Hamburg plant is the facility with the highest energy consumption and the highest emissions within the Tesa production network. To date, a large portion of the process heat for adhesive tape production has been generated using fossil fuels. The company’s transformation strategy now combines electrification, hydrogen, thermal storage, and AI-based control. The “Energy Intelligence” platform integrates data from energy infrastructure, production, and energy markets.
In the future, hydrogen is intended to replace fossil fuels in areas where heat and steam supply cannot be fully electrified . TwoH2-ready dual-fuel steam boilers provide the technical infrastructure for hydrogen use; the first one has already been installed and connected. At the same time, Tesa is preparing to connect its plant to the Hamburg Hydrogen Industry Network ( HH-WIN).
The transformation is supported by a climate protection agreement from the Federal Ministry for Economic Affairs and Energy, as well as local funding from the Hamburg Investment and Development Bank (IFB Hamburg).
Supply Contract Follows Agreement with Salzgitter
Dohler explained: “With Tesa, another industrial customer—following Salzgitter AG—has opted for renewable hydrogen from EWE.”
EWE had signed the supply contract for this project together with Salzgitter AG’s subsidiary, Salzgitter Flachstahl GmbH, in June 2026 (as reported by H2News). Starting in 2030, 10,000 metric tons of hydrogen are expected to be supplied annually from Emden for use in steel production. The plan is to use thehydrogen in the SALCOS program (Salzgitter Low CO2 Steelmaking).
(Source: Tesa SE/ 2026)