Construction of the “H₂Coastlink 1” hydrogen pipeline has begun in Moormerland, East Frisia. The project owner is GTG Nord. EWE NETZ is handling the planning and construction on behalf of GTG Nord. Both companies are part of the EWE Group.
The start of construction was preceded by a five-month approval process. Five months elapsed between the submission of the planning approval documents and the planning approval decision.
Electrolyzer in Emden Connects to the Main Grid
The pipeline is intended to connect a 320-MW electrolyzer in Emden to the core hydrogen network. In the future, approximately 26,000 metric tons of hydrogen per year are expected to be transported from the electrolyzer via this route. The hydrogen pipeline has a transport capacity of over 70,000 metric tons of hydrogen per year.
Additional components of the hydrogen infrastructure are to be connected to the pipeline. These include the project HyperLink project by Gasunie Deutschland and the North Sea-Ruhr Link IV planned by OGE .
The Leer County Administration is in talks with EWE regarding possible branch lines along the route. The goal is to connect regional businesses to the hydrogen supply.
The energy supplier and Salzgitter AG have signed a supply agreement.Starting in 2030, green hydrogen from Emden will be supplied to the steel production facilities in Salzgitter. The agreement highlights the industry’s demand for hydrogen transport capacity.
Funding through the IPCEI Program
“H₂Coastlink 1” is part of the“Clean Hydrogen Coastline”project and is funded by the federal government and the state of Lower Saxony as part of the IPCEI hydrogen program. The European Commission granted state aid approval for the German IPCEI hydrogen projects in February 2024. The project is intended to support the development of a hydrogen economy in northwestern Germany.